Client: Reland plc
Location: Yorkshire Chemicals, Leeds (Kirkstall & Hunslet)
Duration: 26 weeks each
Project Value: £1.5m

reland

• Principal Contractor role

• Demolition and site clearance of a 12 acre & 15 acre sites formerly used for chemical dye production

• Installation of temporary works

• Significant environmental monitoring due to proximity to River Aire and Leeds Liverpool Canal

• Disconnection and termination of all live services

• Protection of existing drains and gullies

• Extensive removal of asbestos and other contaminated materials

• Dismantling of plant and equipment

• Recycling of demolition waste

• Long reach demolition techniques employed

• Removal of slabs, foundations and basements across site

• Crushing, screening and stockpiling of demolition arisings for re-use