Demolition Services Ltd. were contracted to demolish the well publicised Moss Side District Shopping Centre, together with surrounding high rise tower blocks.

 

The 12 month contract was for Manchester City Challenge winner Hulme Regeneration.

The works comprised the demolition of a number of 17 storey and 10 storey tower blocks constructed of a proprietary pre-cast access deck system, together with the demolition of the nearby two storey steel framed Shopping Centre and Market Hall.

Works were carried out involving traditional mechanical demolition techniques together with the controlled use of explosives.

The works also involved the re-cycling of some 150,000 tonnes of demolition rubble for use as backfill to the existing basement, exposed during the course of the Shopping Centre demolition. This ensured a fast transition into the new High Street and Shopping Centre as part of the revamped Hulme Estate.


Click the button below to view a small video clip of part of the Moss Side demolition. Note that the file is approximately 160K and may take a moment or two to download depending upon the speed and quality of your connection.