Case Study – GMI Construction

Case Study – GMI Construction

break-line

gmi-partner-logo

Client: GMI Construction
Location: Holliday Dyes & Chemicals, Huddersfield
Duration: 26 weeks
Project Value: £1.2m

GMI-construction

• Demolition, clearance and ground preparation of over 30 buildings (comprising warehouses, offices, tank farms, process & production plants) on the former 30 acre chemical plant in Huddersfield

• Constrained site by adjacent roads, industrial premises and commercial office properties

• Extensive removal of asbestos including AIB, asbestos limpet, vessel lagging and asbestos lagged pipe work

• Dismantling, including craneage lifts, of plant and equipment

• Explosive demolition of 40m chimney

• Removal of slabs, foundations and basements across site

• Crushing, screening and stockpiling of demolition arisings for re-use